2021 ROAD WORK SCHEDULE
The following roads are scheduled for surface repair work in the upcoming season. Treatment will include the following.
Mill/Fill- Process involves milling approx. 1.5” of road surface and fill with new layer of asphalt. This process is performed on roads that has a good base but wearing surface is damaged.
Reclaim- Entire road surface will be pulverized and regraded, followed by installation of 3” of new asphalt. This process is performed when road surface is severely deteriorated.
Chip Seal- Installation of a adhesive sealing agent and layer of small stone that provides a new wearing surface. This process is performed to extend life of road before paving is required.
Mill/Fill
Hurd Bridge Road | Glenwood Road |
Commerce Street | Grove Street |
Dan Vece Jr Way | |
Re-Claim
Grove Hill Road | Lochbourne Drive |
Leffingwell Road | Vine road |
Pine Place | Fieldbrook Avenue |
Oakwood Lane | Maple Avenue |
Chip Seal (August 2021)
Elsie Lane | James Vincent Drive |
Kristen Way | Ben Merrill Road (partial) |
This list was generated utilizing our current road study and in conjunction with the work that was recently performed by CT Water Company.