The following tentative schedule for the Town Marina Dredging Project is subject to weather conditions and equipment stability. Please keep in mind, dredging will be taking place 24 hours a day, seven days a week in order minimize costs and to expedite the project for completion before winter weather starts. There will be some noise, which is unavoidable, in the area during the dredging operations,. If you have any questions or concerns please contact the Department of Public Work
- October 4th - October 7th: Town docks and piles removed and stored.
- October 6th – TBD: Boat ramp closed for safety.
- October 8th - October 21st: dredging operations 24 hours a day.
- October 25th - October 28th:Reinstallation of Docks and Piles
- November 3rd: Project Finished